Energy & Power Generation Consulting,
Engineering & Management Services

1-888-705-0072

Solutions

PROJECT: Gas Turbine Refurbishment & Turbine/HRSG Controls Upgrade Project

This State Prison was a facility that had a single 3.0 MW Centaur 40 Solar Turbine exhausting heat into its own Heat Recovery Steam Generator (HRSG). Steam produced from the HRSG was used for facility heating, laundry cleaning, kitchen dish washing, and food preparation. The facility has a central power house that also serves as the electrical distribution hub for switchgear control between the gas turbine/generator, the local utility power, and additional high voltage load feeder breakers.

The original system was installed in the mid 1980's and ran almost continuously until the year 2005 at which time the turbine had in excess of 50,000 operating hours. Solar Turbine requires a complete turbine overhaul when the operating hours exceed this standard operating limit. The gas turbine/HRSG system was abandoned and steam was produced out of a single standby package boiler. Due to problems with this package boiler, that at times left the facility without heating steam, The State issued an emergency contract to refurbish the gas turbine, upgrade the turbine controls from the old hardwired relay logic to a PLC controlled system, and upgrade the HRSG controls from the old Bailey single loop controllers. Engineering services were provided to manage the turbine controls subcontractor and to be the primary control system design engineer for the HRSG controls upgrade.

Some of the key features used within the turbine controls were the standard start/stop logic but of special interest was the automated generation load control and the Wet-Nox controls. The engineering service was responsible to coordinate the turbine controls subcontractor on these key features since they did not have much experience with this type of generation in this west coast state. The load controls were design around the strategy of maintaining the paralleled utility power at a set point of approximately 100 kW. Therefore, as the prison facility's load would change, the gas turbine/generator would swing to meet the facility's load and maintain the utility power near it's operator set point.

The State air emission's requirements for this unit specified that for every pound mass of fuel burned an equivalent pound mass of water and was to be injected into the combustion process to maintain exhaust Nox levels within source tested standards. Therefore, engineering service created the control loop design using new process parameters to improve stability within the control loop. The previous Solar Turbine design required constant online operator interaction to maintain the one-to-one ratio of water to fuel. The new Nox controls have achieved zero operator interaction because of this improved design.

The Heat Recovery Steam Generator (HRSG) control system upgrade portion of this project provided an opportunity to install advanced energy anticipation control philosophy for a much needed requirement of stable steam generation. The previous control system was so unstable, the alarm acknowledge push button had been worn off the old controller faceplate! This HRSG configuration also employed the use of a natural gas fired duct burner to supplement the heat energy of the gas turbine exhaust for steam production. The new control system design utilized a similar mode of operation as the original design and was called "single element" control where this "element" was the steam pressure process variable. In addition, the new control logic design utilized a much more anticipatory control philosophy using four elements of process variables to correctly modify the energy demand signal to the diverter valve/duct burner combination in anticipation of process disturbances. The logic allowed the operator to conduct a bumpless "flying swap" between either of these modes. The improved stability was the first this site had seen since the original commissioning of the unit!

Lastly, the engineering service was the control system engineer that correctly identified the requirement to upgrade the existing gas turbine hydraulic starter system to an Allen-Bradley PowerFlex Variable Frequency Drive(VFD), provided the installation design sketches, coordinated the installation construction, determined and programmed the VFD configuration parameters, and successfully started and commissioned this device.

RESULTS


• Provided a complete hands on training class for the control system upgrades to the turbine and Heat Recovery Steam Generator (HRSG). This scope included all formal written material and conducting three full days of classes.