![]() Solar Centaur 40 Gas TurbinePROJECT: Gas Turbine Refurbishment & Turbine/HRSG Controls Upgrade ProjectThis State Prison was a facility that had a single 3.0 MW Centaur 40 Solar Turbine exhausting heat into its own Heat Recovery Steam Generator (HRSG). Steam produced from the HRSG was used for facility heating, laundry cleaning, kitchen dish washing, and food preparation. The facility has a central power house that also serves as the electrical distribution hub for switchgear control between the gas turbine/generator, the local utility power, and additional high voltage load feeder breakers. The original system was installed in the mid 1980's and ran almost continuously until the year 2005 at which time the turbine had in excess of 50,000 operating hours. Solar Turbine requires a complete turbine overhaul when the operating hours exceed this standard operating limit. The gas turbine/HRSG system was abandoned and steam was produced out of a single standby package boiler. Due to problems with this package boiler, that at times left the facility without heating steam, The State issued an emergency contract to refurbish the gas turbine, upgrade the turbine controls from the old hardwired relay logic to a PLC controlled system, and upgrade the HRSG controls from the old Bailey single loop controllers. Engineering services were provided to manage the turbine controls subcontractor and to be the primary control system design engineer for the HRSG controls upgrade. Some of the key features used within the turbine controls were the standard start/stop logic but of special interest was the automated generation load control and the Wet-Nox controls. The engineering service was responsible to coordinate the turbine controls subcontractor on these key features since they did not have much experience with this type of generation in this west coast state. The load controls were design around the strategy of maintaining the paralleled utility power at a set point of approximately 100 kW. Therefore, as the prison facility's load would change, the gas turbine/generator would swing to meet the facility's load and maintain the utility power near it's operator set point. The State air emission's requirements for this unit specified that for every pound mass of fuel burned an equivalent pound mass of water and was to be injected into the combustion process to maintain exhaust Nox levels within source tested standards. Therefore, engineering service created the control loop design using new process parameters to improve stability within the control loop. The previous Solar Turbine design required constant online operator interaction to maintain the one-to-one ratio of water to fuel. The new Nox controls have achieved zero operator interaction because of this improved design. The Heat Recovery Steam Generator (HRSG) control system upgrade portion of this project provided an opportunity to install advanced energy anticipation control philosophy for a much needed requirement of stable steam generation. The previous control system was so unstable, the alarm acknowledge push button had been worn off the old controller faceplate! This HRSG configuration also employed the use of a natural gas fired duct burner to supplement the heat energy of the gas turbine exhaust for steam production. The new control system design utilized a similar mode of operation as the original design and was called "single element" control where this "element" was the steam pressure process variable. In addition, the new control logic design utilized a much more anticipatory control philosophy using four elements of process variables to correctly modify the energy demand signal to the diverter valve/duct burner combination in anticipation of process disturbances. The logic allowed the operator to conduct a bumpless "flying swap" between either of these modes. The improved stability was the first this site had seen since the original commissioning of the unit! Lastly, the engineering service was the control system engineer that correctly identified the requirement to upgrade the existing gas turbine hydraulic starter system to an Allen-Bradley PowerFlex Variable Frequency Drive(VFD), provided the installation design sketches, coordinated the installation construction, determined and programmed the VFD configuration parameters, and successfully started and commissioned this device. RESULTS• Successfully designed an innovative and stable multi-mode Plant Master analog control logic for regulation of steam delivery from the HRSG. This logic incorporated predictive control loops using 4 elements of analog process inputs. • Performed all of the control logic programming for both upgraded HRSG controllers (Plant Master & Drum Level) using Preferred Instruments PC-3 Draw and PC-3 Edit programs. This documentation was a translation of the completed designed simple SAMA logic. • Provided review of the turbine control system subcontractor's drawing submittals to verify accuracy to the existing electrical design, to the logic design, and input/output list for the new Allen-Bradley ControLogix PLC. • Designed the full control system logic for the "Wet-Nox Water Injection" for a Solar Turbine Centaur 40. The original logic didn't work. Improved process indications were used combined with new logic to create a very stable and effective control system. • Completed a successful startup and commissioning of the upgraded control system for the Solar Centaur 40 gas turbine. Complete automatic operation to full load was achieved for all systems including the Wet-Nox system. • Completed a successful startup and commissioning of the upgraded control system for the HRSG. This included advance 4 element control for the Plant Master switchable to single element on the fly and commissioning the Drum Level controls. • Completed a conversion of the Solar Turbine Centaur 40 hydraulic starter system to a Variable Frequency Drive (VFD). Provided the electrical design sketches, supervised construction, determined and conducted VFD programming config's, & S/U. PROJECT: State Prison Solar Turbines (2) Maintenance ServicesThis State Prison was a facility that has two 3.0 MW Centaur 40 Solar Turbines with each turbine exhausting heat into its own Heat Recovery Steam Generator (HRSG). Steam produced from the HRSG was used for facility heating, laundry cleaning, kitchen dish washing, and food preparation. The facility has a central power house that also serves as the electrical distribution hub for switchgear control between the two gas turbine/generators, local utility power, and four additional high voltage load feeder breakers. Three years prior (at the end of 2004), The State completed a major turbine, turbine controls, and facility control system upgrade. The goal of the 2004 project was to fully automate the dispatching of the two gas turbine/generators based on facility loads such that the local utility power consumption was held at a fixed operator set point of approximately 300 kW. The operator would select the lead/lag assignment between the two turbines and the automatic controls would start/stop the lag turbine based on the facilities change in load demand always attempting to maintain 300 kW of "import" power from the local utility power source. Engineering services were required to resolve instabilities resulting from the automatic controls not correctly controlling the gas turbines. The State was unsuccessful at forcing the original contractor to resolve final commissioning instabilities in the 2004 upgrade project. The primary load and switchgear breaker control system logic was performed in PLC style controllers supplied by ENCORP. The Solar Turbine logic was resident in Allen-Bradley PLC-5's and obtained direct on/off digital commands and an analog kW set point from the ENCORP PLC's. The engineering services successfully diagnosed numerous tedious logic errors, incorrect tuning values, and design flaws that all contributed to, at times, very severe load instabilities. Prior to these improvements, the units always ran in manual with the operator performing all load changes through 15 minute periodic inspections of the facility load requirements. Now the units run in full automatic and the site operators have stated they have never seen this good a performance in the machines since their original commissioning. RESULTS• Successfully corrected the corruption of the configuration program for the site's gas turbine Variable Frequency Drives (VFD). These units supplied by Solar Turbine were used for the starter system and communciated via A/B ControlNet 1.25 to the PLC-5. • Correctly diagnosed and replaced an ENCORP GPC unit. Worked with the ENCORP field engineer to transfer correct programming software, obtained communication capabilities with a laptop, and was able to perform diagnostics and tuning changes. • Correctly diagnosed a failed LonTalk adapter interface (the pcimia PCC-10) card for the ENCORP communication device to the UPC and two GPC's. Correctly replaced with a LonTalk SLTA-10 adapter, installed the software configuration, and commissioned. • Completed a study of the functional logic for load shedding existing within a problematic design, built a complete bench test system including real world simulation, and redesigned the logic to meet the site's load shedding requirements. |